Under Construction |
The Foundation, Part II |
I calculated the volume of the piers and placed the order for fifteen yards of concrete and a pumper truck. Owl arrived spot-on-time at 6:15 and the concrete half an hour later. Owl worked the pumper's controls, I dragged the hose around filling the piers by thirds, and Till vibrated the mud in between each round. By the time the rains came, we were nearly finished. |
|
|
Due to the moisture in the soil, the bottom of the southeast sonotube became saturated and began to disintegrate. Not long after I had filled that pier to the top, the base of the sonotube exploded and released the concrete into the surrounding hole. I watched in horror as the surface level dropped two feet. |
|
Fortunately I had over-estimated the concrete by half a yard; I refilled that pier as Owl jumped up and down, hollering over the pulsing sound of the pumper that the concrete truck was running dry. |
Two days later I set the steel I-beams. When I placed the steel order I identified the beams by letters of the alphabet, as each beam had either a different length, load bearing capacity, or bolt hole configuration. I dragged each beam to its location: "A" here, then "B", then for some reason, "H". I threaded a nut down the anchor bolts, set a steel plate onto the nuts, then set the I-beam onto that. Next I used a wrench to raise or lower the nuts to level and align the I-beam. Once the beam was in correct position, I tightened the top nuts. I filled the gap beneath with concrete to create a load-bearing bed. |
|
|
Where the three cross-beams met the existing house I chiselled away the cement block to create a pocket and seat. Each cross-beam sat on a mortar bed and bolted to the existing cement block foundation. I now had a rigid and secure gridwork over which to lay my floor joists. |
|
Foundation II
|
© yer everlovin' Tboy productions, 2003
|